An engineering change order, or ECO, is the instruction to put an approved revision into effect.

By Teebling Editorial
What Is an Engineering Change Order? How to Change an OEM Spec After Approval

An engineering change order, or ECO, is the instruction to put an approved revision into effect. It tells production what changes, what does not and which units must follow the new version. A marked-up drawing can start that conversation, but does not tell the materials team what to do with the old stock. The order should cover that transition as well as the technical fix.

Describe the problem and the approved change separately

Suppose a bag adjuster has a nominal 25 mm strap and feeds correctly on a single layer but jams when a folded end passes through. Record the failing sample, the exact webbing construction and the condition that reproduced the jam. The proposal could enlarge the usable throat or change the folded end. Approve one option against a fitted sample. The ECO should name the chosen revision; do not send a factory both suggestions in the production instruction.

RecordExample decision
Current baselineBuckle drawing B and its accepted bag sample
New baselineDrawing C changes the throat; strap width, color and outer shape are unchanged
Effective pointStart with the next identified cutting or assembly lot after sign-off
Open inventoryCount revision B separately. Hold it until its order allocation is decided
VerificationMeasure the revised throat and check the actual webbing feeds and locks in the finished bag

Check the implementation at the first affected lot

A planner updates the BOM and receiving reference. The line removes the old fitting and has the new drawing and reference where the part is issued. Quality verifies units from the first affected lot. A date printed on the ECO is not evidence of implementation: ask for a part, photo and lot record showing the new construction went where intended. Make sure the packaging and the buyer’s ERP have not kept a discontinued variant description.

Use the wholesale bags collection to indicate the type of assembly in the request, then list the exact existing style and proposed affected part. If the order has different strap constructions, check each that uses the revised adjuster. A change that helps a thick folded end can introduce slip on thinner webbing.

What if the change is needed for one shipment only?

Ask for a separately approved, time-limited exception describing the exact units and reason. Do not silently make that exception the new specification. Record whether the next lot returns to the old revision or requires a permanent ECO.

Review a change to an approved product

Share this articleLinkedIn ↗WhatsApp ↗
LET'S TALK PRODUCTS

Have a project in mind?

Share your product reference, customization needs and order quantities with our team.

Welcome Guest!
Request B2B Quote